2020 Report for Arch Street

Year
2020
Number of volunteers
11
Total volunteer hours
34
Number of events
3
Number of trees planted
0
Number of shrubs planted
0
Number of perennials planted
0
Yards compost spread
0.00
Yards mulch spread
1.00
Summary
Arch Street spent its time this summer cleaning up trash and clearing out overgrowth. The group had two successful community planning meetings to discuss issues of drug use and vagrancy in the park. They had two workdays clearing out multifloras rose and overgrowth on the edges to increase visibility in the park. The second planning meeting involved representatives of the Liveable City Initiative to advocate for the removal of a dead tree and a gate with a lock to discourage drug use and littering.